PRODUCTION PLANNING REPORT

Proposed quantities:
  P1: 20
  P2: 20
  P3: 20
Resource usage (capacity):
  MachineHours: 80 (90), feasible=True
  LaborHours: 100 (110), feasible=True
  MaterialUnits: 80 (100), feasible=True
Proposed plan feasible: True
Solution to A @ x = b:
  P1: 20.0000
  P2: 20.0000
  P3: 30.0000
Equation verified: True
Nonnegative quantities: True
Integer quantities: True
Note: solving equations is not a profit optimization problem